An offshore administrator can do almost all the paperwork behind a progress claim: build the claim, gather the photos, dockets and signed variations that back it, keep the variation and retention registers current, and chase what is late. What they cannot do is decide anything — how much a subcontractor is owed, what you withhold, when the claim goes out, or when the money is released. The deadlines come from the state the job is in rather than from any national rule, so you, your contract administrator or your lawyer write the dates out once per contract and the administrator works to them. Write that split down before anyone starts and the role is safe.
The question builders arrive with is whether someone offshore can prepare progress claims without exposing them under the security of payment legislation. They can prepare nearly all of it and decide none of it: the assembly, the backup, the registers and the diary travel, while what you claim, what you withhold and when you serve stays with you.
That split is not a hedge. It is the only version that survives contact with the Acts, which attach hard consequences to dates and to content, and those consequences land on you.
The calendar is most of the job
Security of payment in Australia is state and territory based. There is no national Act, the terminology is inconsistent, and a process learned on a Queensland job does not transfer cleanly to one in Perth.
| Where the work is | The Act that applies |
|---|---|
| New South Wales | Building and Construction Industry Security of Payment Act 1999 |
| Victoria | Building and Construction Industry Security of Payment Act 2002 |
| Queensland | Building Industry Fairness (Security of Payment) Act 2017 |
| Western Australia | Building and Construction Industry (Security of Payment) Act 2021 |
| South Australia | Building and Construction Industry Security of Payment Act 2009 |
| Tasmania | Building and Construction Industry Security of Payment Act 2009 |
| Australian Capital Territory | Building and Construction Industry (Security of Payment) Act 2009 |
| Northern Territory | Construction Contracts (Security of Payments) Act 2004 |
Western Australia brought its 2021 Act in progressively, so an older contract there may still sit under the legislation that preceded it. Confirm which one yours falls under.
So the first thing an administrator establishes on a new contract is which rule book it sits under, and the second is never to assume it matches the last one.
Missing a window is not a telling-off. Under section 14 of the New South Wales Act, a respondent served with a payment claim who does not provide a payment schedule within ten business days of service, or within the shorter period the contract allows if there is one, becomes liable to pay the claimed amount on the due date for that progress payment. Other jurisdictions run their own version of the same idea with different windows and different mechanics. The dates that bind you are the ones in your Act and your contract, and they should come from your contract administrator or your lawyer, not from an article.
Who owns the dates
Here is the rule that makes the whole arrangement safe. Your administrator never calculates a statutory date from first principles.
You, or your contract administrator, or your lawyer, sit down once per contract and write the dates out. When a claim can be served. The method of service the contract and the Act permit. The window you have to respond to a subcontractor's claim. The payment due date. That is one short sitting, done by someone qualified to do it, and it is the input to everything else.
From there the job is mechanical. One row per contract, and each key date carries two reminders in front of it: one to start assembling the pack, one for the day it has to be complete and in front of you. Nothing is served on the day it falls due, because photographs arrive late and site supervisors go quiet. Anything that cannot be reconciled stops and comes back to you: a stage that looks incomplete, a variation with no written approval, a clause that sits oddly against the Act.
Service method deserves its own habit. Contracts and the Acts commonly specify how a document may be served, and the method can matter as much as the date. Record the permitted method next to the date, and log what was sent, to whom and when.
What an offshore administrator actually prepares
Everything in this list is preparation. None of it is a decision.
- The claim itself, built against the schedule of works and the stage actually reached, in the format and to the timing your contract requires.
- The supporting pack: dated site photographs, delivery dockets, signed variation approvals and the subcontractor claims behind your figure, indexed so it can be produced fast if the claim is contested.
- The variation register, kept current, showing each variation's status, price, approval evidence and whether it has been claimed yet.
- Retention: what is held, on which job, under which clause, and the date it falls due for release.
- Incoming subcontractor claims, checked against the order, the work in place and the retention held, with a draft payment schedule and draft reasons prepared for you to assess, amend and sign.
- The diary, the part most builders underrate and the part that pays for the role.
That is the shape of the progress claims and invoicing role. If it also runs to site documentation and requests for information, it sits closer to a project coordinator; if the pressure is on quoting rather than claiming, start with an estimating assistant.
The variation register is where the money is
Approved variations that were carried out, signed off and never claimed are work you have already paid to deliver. They go unbilled for a structural reason rather than a careless one: the person who knows the variation happened is on site, and the person who would invoice it is the same person, at nine at night.
A register fixes it by being boring. Every instruction gets a row on the day it is raised, and every row carries a status. Only four statuses matter: priced, approved, claimed, paid. An administrator who works that register before every claim catches those rows while they are still claimable. Our guide on what a builder should delegate first puts claims and variations second only to estimating preparation for exactly this reason.
Chasing is a real job, and better done by someone who is not you
Follow-up is a cadence, not a confrontation. A fixed sequence of polite, dated, near-identical contacts is easier to sustain than an irritated phone call three weeks late, and it costs less in the relationship, because it reads as a process rather than a complaint. The same discipline applies to debtor follow-up generally.
The other chase is documentation. Subcontractor claims with no docket, variations with no signature, certificates of currency that expired in March. That work overlaps with a compliance administrator, and in a smaller business it is often one person wearing both hats. The escalation rule still has to come from you. They enforce it, they do not invent it.
What does not move offshore
Preparation and chasing travel. Assessment, authorisation and anything with a statutory consequence do not, and the line should be written down before anyone starts.
- What a subcontractor is entitled to. That is a commercial and contractual assessment. Your administrator applies your figure and issues it; they do not arrive at it.
- The decision to serve, and the reasons for withholding. A payment schedule is a statutory document. It can be drafted for you. It is decided by you.
- Contract interpretation. What a clause entitles you to is a question for you or your adviser, not for a search engine.
- Payment authorisation. No offshore team member holds bank authority. They prepare the run, you release it.
- Adjudication. A claim that goes to adjudication is decided by a registered adjudicator appointed through the process your jurisdiction's Act sets out, and that process differs between states. It is never decided in-house and never offshore. Your administrator contributes the evidence pack, ready, because they have been building it all along.
The wider boundary for building work, covering licensing, safety and certification, sits on our construction and trades page.
How the first two months usually run
Weeks one and two are reconstruction. The administrator builds the register from your live jobs, one row at a time, and you supply the dates. They serve nothing. They shadow a full claim cycle you run yourself and write down what you did.
Weeks three and four, they draft and you rewrite. Keep the differences, because they are the training material, and the list gets shorter with each claim. By month two they own preparation and the diary, the pack lands on your desk ahead of the date, and your job shrinks to reviewing and serving. Subcontractor claim checking and retention chasing come after that, once they know your subbies well enough for the chasing to carry weight.
The one thing that derails this has nothing to do with the person doing the work. If nobody on site sends photographs, dockets and confirmed variations to an agreed place, the administrator has nothing to build a claim from, and it looks like they are not proactive when the failure is upstream. Agree that channel in week one. A dated folder and a two-minute voice note at knock-off is enough.
What to do next
Take your two largest live contracts and write the dates out this week, whether or not you ever hand the work to anyone. If a claim window has been sitting unwatched, that is where you find it.
If maintaining that register is the part you know you will not get to, that is the job worth handing over, and it starts from A$14 an hour plus GST for a full-time engagement. Book a 30-minute discovery call and bring one contract with you.
This is general information, not legal or financial advice. Security of payment obligations turn on the Act in your jurisdiction and on your contract, so have your dates confirmed by a qualified adviser before you rely on them.
How we would staff your claim calendar
Everything above sits inside one role. We hire a dedicated progress claims and invoicing administrator in the Philippines on your behalf — full-time, working your hours, inside your systems under their own named login. They own the calendar and the paperwork; you keep every decision that carries a legal or commercial consequence.
- Builds and maintains one row per contract: which state's rules apply, the dates you or your contract administrator wrote out, the service method the contract permits, and two reminders in front of every key date — one to start assembling, one for the day the pack must be in front of you.
- Assembles each claim against the schedule of works and the stage actually reached, with the backup indexed — dated site photographs, delivery dockets, signed variation approvals and the subcontractor claims behind your figure — so it can be produced fast if the claim is contested.
- Works the variation register before every claim, moving each row through priced, approved, claimed and paid, so approved work that was carried out and signed off does not go unbilled.
- Checks incoming subcontractor claims against the order, the work in place and the retention held, then drafts the payment schedule and the reasons for you to assess, amend and sign.
- Tracks retentions by job, clause and release date, and runs the follow-up cadence on late payment and missing documentation — unsigned variations, absent dockets, certificates of currency that expired months ago.
- What a subcontractor is entitled to, and the decision on what to claim, withhold or dispute.
- The statutory dates themselves, written once per contract by you, your contract administrator or your lawyer, plus any question of contract interpretation.
- The decision to serve, and signing the payment schedule — drafted for you, decided by you.
- Payment authorisation and bank access, and anything that goes to adjudication, which is decided by a registered adjudicator and never in-house.
Frequently asked questions
How much does an offshore progress claims administrator cost?
Can an offshore administrator serve a payment claim or sign a payment schedule?
Do offshore construction administrators need a building qualification?
What system access does a progress claims administrator need?
Can one administrator handle jobs in different states?
Do offshore staff work Australian hours for time-critical claims?
- Building and Construction Industry Security of Payment Act 1999 (NSW), s 14 (read with s 15) — The ten business day payment schedule window and the consequence of missing it
- Building and Construction Industry Security of Payment Act 2002 (Vic) — The Act that applies to work in Victoria
- Building Industry Fairness (Security of Payment) Act 2017 (Qld) — The Queensland Act, and that adjudicators are appointed through the process the jurisdiction sets out rather than in-house
- Building and Construction Industry (Security of Payment) Act 2021 (WA), which replaced the Construction Contracts Act 2004 (WA) — The Western Australian Act, and the warning that an older WA contract may still sit under the earlier legislation
- Building and Construction Industry Security of Payment Act 2009 (SA); Building and Construction Industry Security of Payment Act 2009 (Tas); Building and Construction Industry (Security of Payment) Act 2009 (ACT); Construction Contracts (Security of Payments) Act 2004 (NT) — The remaining jurisdictions in the table, and that there is no single national Act
- StaffingSolutions.io — Progress claims and invoicing role, construction and trades — The scope of the role, the boundary on claim assessment and payment authorisation, and the from A$14 an hour plus GST full-time rate
- StaffingSolutions.io — Construction and trades industry page — The wider offshore boundary for building work, including serving and responding to payment claims
